Residents of the Bekkul Baba residential area in Aktobe Region are raising the alarm over the condition of detour roads near the Orsk highway, fearing that the damaged sections will cause accidents once winter arrives and worrying about the safety of children who travel to the city for school every day, the website infohub.kz reports.

According to local residents, road repairs began in late July but the work has dragged on. "Every morning we commute to the city for work, and our children study in the city. The road has been completely torn up. They started repairs in late July and, naturally, they are not going to finish in time. This road is very dangerous in winter. On the bridge detours there is no surface at all, and in winter not a single heavy truck will get through there. The descents and turns are steep, and cars will fly off. This section is dangerous to people's lives and health. In the morning, until 10:00, trucks should not be allowed through at all; deadlines are absolutely necessary. We fear for our children," residents say.

The national company KazAvtoZhol responded that a contract for work on the 763–791 km section of the Aktobe — Karabutak — Ulgaysyn highway was signed with the contractor ASSANA-DorStroy LLP in May. Construction work began in June 2026, and the construction period itself will run until 2029.

"The project provides for raising the technical category of the road from Category III to Category I, including the dismantling of existing bridge and small artificial structures followed by the construction of new ones, as well as the construction of interchanges. In this connection, traffic in the construction areas has been temporarily organized along detour roads. The deterioration of the detour roads and the formation of unevenness are linked to intensive heavy truck traffic, high axle loads and unfavorable weather conditions," KazAvtoZhol said.

The company added that the contractor periodically carries out maintenance on the detour roads and the existing sections of the highway, including profiling the roadway and eliminating unevenness.

"The contractor was issued remarks regarding the condition of the detour roads and was required to promptly eliminate the identified deficiencies, as well as to take additional measures to ensure safe and uninterrupted vehicle traffic, especially in the coming winter period," KazAvtoZhol noted.