Almaty is building three new metro stations as part of the third phase of the first line of its subway system, with the section set to run from Qalqaman station to the Barlyq market. The Municipal State Enterprise "Metropolitan" provided details on the ongoing work at the future underground facilities and their launch timeline, infohub.kz reports.

According to the metro's press service, the stations do not yet have official names and are designated as Station I, Station II and Station III. Official names will be approved in accordance with established procedures.

The stations are arranged as follows. Station I is on Alatau Avenue, north of Abai Avenue and south of Sabdenov Street, near the akimat of the Nauryzbai district. Station II is on Alatau Avenue at its intersection with Tole Bi Street. Station III is on the grounds of the Barlyq market.

The Municipal State Enterprise "Metropolitan" also disclosed the stage of work at each site. At Station I, utility relocation work has already been completed, specifically for power supply and a gas pipeline. A bypass road has been completed here, and excavation work is beginning.

At Station II, utility relocation and bypass road work are in the final stages. As for Station III, excavation and concrete work are underway, including concreting of the vestibule and the platform section.

The press service said construction of the section is planned for completion in 2029.