Attracting investment, expanding domestic production and modernizing infrastructure remain among the priorities for developing Kazakhstan's agro-industrial complex. The country continues to implement projects aimed at increasing agricultural output, improving storage conditions and developing logistics. As part of this effort, two facilities with a combined value of 19.3 billion tenge are being built in Almaty Region, infohub.kz reports.
The bulk of the investment — 17.3 billion tenge — is going toward the ALATAU GREEN PRODUCTION greenhouse facility. Once operational, it is expected to supply up to four thousand tonnes of vegetables to the market each year.
The complex is being built on a 16-hectare site. The project provides for two types of greenhouse zones — winter and summer. In addition to the main production areas, separate facilities will be equipped for growing seedlings and producing salad crops.
Particular attention has been paid to organizing storage of the harvested crops. A warehouse complex will be built on the site. Its capacity will allow up to 6,000 tonnes of vegetables to be kept in long-term storage and more than 700 tonnes of fruit in short-term storage.
Work at the site is nearing completion. Construction readiness has reached about 80%. The glass greenhouses have already been erected, and workers are now laying underground utility lines. The complex is scheduled to open next year.
In parallel, Almaty Region is creating conditions for more efficient handling of grain products. A production and logistics complex of the company ТОО «СТРОЙИНВЕСТ — TS» is being built in the Kairat industrial zone. The project is worth 2 billion tenge.
Grain storage facilities with a total capacity of 10,000 tonnes will be located on the allocated site. The facility's capabilities will not be limited to storing and receiving grain: its designed annual shipment capacity will reach 200,000 tonnes.
Work to create the necessary infrastructure is almost complete. The railway tracks are already in place, and connection to the gas network is in its final stage. The main construction and installation work is also nearing completion.