A specialized inter-district economic court in Kostanay region has rejected a contractor's claim for an additional agreement on the construction of a 980-seat secondary school in the Bereke microdistrict of Kostanay, the Kostanay region courts' official Telegram channel reported, according to infohub.kz.
The dispute centered on additional construction work worth 471.8 million tenge that the contractor performed beyond the scope stipulated in the public procurement contract. The contractor had sought to recover the funds through court, but the claim was dismissed.
During the proceedings, the court found that the legally prescribed procedure for increasing the contract price had not been followed: the design and estimate documentation was not adjusted, the project cost was not increased, and no additional financing was allocated in the manner required by law.
The court emphasized that the actual performance of additional work and its objective necessity do not by themselves create financial obligations for the state customer. The amount of a public procurement contract may be changed only in compliance with legal requirements.
It was also noted that the contractor, having failed to obtain proper approval for the additional work, continued to carry it out at its own entrepreneurial risk.