Almaty's Department for Traffic Management and Passenger Transport has responded to an official inquiry from a NUR.KZ correspondent, disclosing details of the LRT construction that will run along several city streets, the website infohub.kz reports.
Concrete slabs will be laid on the LRT tracks on block-to-block sections along Momyshuly and Tole bi streets. "The slabs will be laid on the top layer of the crushed-stone base when the upper track structure is formed. The color scheme, design and pattern combinations are currently at the approval stage. Since the concrete slabs will be located on sections between intersections, pedestrian and vehicle traffic over them is not envisaged," the department explained.
The department said slabs were chosen over asphalt because the tracks require regular technical maintenance, including leveling and tightening of fasteners, which will make operational work easier. On Ablaykhan Avenue from Tole bi Street to the Almaty-2 railway station, by contrast, no slabs will be used; the surface will be made of asphalt concrete at the same level as the roadway.
Pedestrian crossings will be provided for passengers to reach the stop islands, and special curbs will separate the LRT line from the roadway. However, they will not be installed at intersections.
As for rolling stock, the first phase of the LRT is to be served by trains purchased from the Chinese company CRRC. According to the department, each train will consist of five sections and be designed to carry 283 passengers. A total of 25 trainsets is planned for purchase. The expected headway between trains will be 5-7 minutes.
Meanwhile, earthworks are already under way in the industrial zone of the Alatau district, including leveling of the land plot for the subsequent construction of depot facilities. The depot is expected to occupy 19 hectares of land.
Recall that Almaty's LRT line is planned to be launched at the end of 2027. The first phase of the first LRT line will be entirely above ground.
The first phase of the first LRT line begins at the depot located in the industrial zone of the Alatau district near the intersection of Monke bi and B. Momyshuly streets. The route then runs along B. Momyshuly Street to Tole bi Street, then east along Tole bi Street to Abylai Khan Avenue and on along Abylai Khan Avenue to the Almaty-2 railway station. The terminal station is to be the Raiymbek batyr transport and interchange hub.
It was also reported that one LRT trainset in the southern capital will be able to carry 285 passengers. The average speed will be 35 km/h. In September this year, rails began to be laid on the tracks.